Project Cost
Construction Cost: $4,226,163
Consultant & Soft Costs: $853,144
Total Project Cost: $5,079,306
| New Construction | |||
| Music/Children Building | 22,847 |
$150.00 |
3.427,050 |
| Main Street Covered Walk | 257 |
$150.00 |
38,550 |
| Porte-Cohere | 762 |
$75.00 |
57,150 |
| Chapel Renovation | 6,880 |
$125.00 |
860,00 |
| Sub-Total | 4,832,750 |
||
| Site Cost (utilities, paving) | 350,620 |
||
| Design Contingency | 5% |
279,669 |
|
| Total | 4,733,370 |
||
| Construction Contingency | 5% |
236,669 |
|
| Total Construction Cost | 4,970,039 |
||
| Owner's Cost | 18% |
894,607 |
|
| Total Building Cost | 5,864,645 |
Please note: Owners Costs includes costs for Professional Fees, Fund Raising Expenses, Furnishings and Equipment, Permitting Fees, Government Review Fees, Testing Expenses, Survey Expenses, etc.